SPECIAL INSTRUCTIONS FOR PRICING ALL
SERVICES AND SUPPORT PRODUCTS
(1) Costs incurred for transportation and per diem (lodging,
meals and incidental expenses) will be billed in accordance with
the regulatory implementation of Public Law 99-234, FAR 31.205-46
Travel Costs, and the contractor's cost accounting system. These
costs are directly reimbursable by the ordering agency.
(A) The contractor shall notify the ordering agency,
in writing, of the requirement for reimbursement of transportation
and per diem expenses, prior to acceptance of the order. This
notification shall include a “not to exceed” estimate
of these proposed costs. Any applicable indirect costs associated
with the transportation and per diem expenses will be charged
at a rate negotiated prior to the using agency's delivery order.
Contractors shall be reimbursed only for incurred costs at or
below the “not to exceed.”
(B) Costs for transportation, lodging, meals, and incidental
expenses incurred by contractor personnel on official company
business are allowable subject to the limitations contained in
FAR 31.205-46, Travel Costs.
(C) Reimbursements for costs that are not specified in
this solicitation, or in any contract or task order resulting
from this solicitation, are not allowed. It is GSA policy NOT
to allow a charge of profit or fee on reimbursable items. No
reimbursement will be made for a contractor's local travel (such
as mileage to and from a local site).
NO REIMBURSEMENT IS AUTHORIZED EXCEPT AS SPECIFIED IN AN ORDERING
AGENCY'S TASK ORDER.
(2) The preferred type of Task order issued against the
contract is Firm Fixed-Price. However, Labor-Hour Task orders may
be issued where circumstances dictate, as determined by the ordering
agency Contracting Officer, provided a determination is made in
accordance with FAR 16.601(b) and 16.601(c).
LICENSING FEES:
Licensing fees are to be negotiated with users separately outside
of this Federal Supply Schedule. GSA will not negotiate or award
licensing fees of any type.
52.242-13 BANKRUPTCY (JUL 1995) 42.903
In the event the Contractor enters into proceedings relating to
bankruptcy, whether voluntary or involuntary, the Contractor
agrees to furnish, by certified mail or electronic commerce method
authorized by the contract, written notification of the bankruptcy
to the Contracting Officer responsible for administering the
contract. This notification shall be furnished within five days
of the initiation of the proceedings relating to bankruptcy filing.
This notification shall include the date on which the bankruptcy
petition was filed, the identity of the court in which the bankruptcy
petition was filed, and a listing of Government contract numbers
and contracting offices for all Government contracts against
which final payment has not been made. This obligation remains
in effect until final payment under this contract.
52.219-16 LIQUIDATED DAMAGES-SUBCONTRACTING
PLAN (JAN 1999) 19.708(b)(2)
(a) “Failure to make a good faith effort to comply
with the subcontracting plan”, as used in this clause,
means a willful or intentional failure to perform in accordance
with the requirements of the subcontracting plan approved under
the clause in this contract entitled “Small Business Subcontracting
Plan,” or willful or intentional action to frustrate the
plan.
(b) Performance shall be measured by applying the percentage
goals to the total actual subcontracting dollars or, if a commercial
plan is involved, to the pro rata share of actual subcontracting
dollars attributable to Government contracts covered by the commercial
plan. If, at contract completion or, in the case of a commercial
plan, at the close of the fiscal year for which the plan is applicable,
the Contractor has failed to meet its subcontracting goals and
the Contracting Officer decides in accordance with paragraph (c)
of this clause that the Contractor failed to make a good faith
effort to comply with its subcontracting plan, established in accordance
with the clause in this contract entitled “Small Business
Subcontracting Plan,” the Contractor shall pay the Government
liquidated damages in an amount stated. The amount of probable
damages attributable to the Contractor's failure to comply shall
be an amount equal to the actual dollar amount by which the Contractor
failed to achieve each subcontract goal.
(c) Before the Contracting Officer makes a final decision
that the Contractor has failed to make such good faith effort,
the Contracting Officer shall give the Contractor written notice
specifying the failure and permitting the Contractor to demonstrate
what good faith efforts have been made and to discuss the matter.
Failure to respond to the notice may be taken as an admission that
no valid explanation exists. If, after consideration of all the
pertinent data, the Contracting Officer finds that the Contractor
failed to make a good faith effort to comply with the subcontracting
plan, the Contracting Officer shall issue a final decision to that
effect and require that the Contractor pay the Government liquidated
damages as provided in paragraph (b) of this clause.
(d) With respect to commercial plans, the Contracting
Officer who approved the plan will perform the functions of the
Contracting Officer under this clause on behalf of all agencies
with contracts covered by the commercial plan.
(e) The Contractor shall have the right of appeal, under
the clause in this contract entitled Disputes, from any final decision
of the Contracting Officer.
(f) Liquidated damages shall be in addition to any other
remedies that the Government may have. 52.222-1
52.222-1 NOTICE TO THE GOVERNMENT OF
LABOR DISPUTES (FEB 1997) 22.103-5(a)
If the Contractor has knowledge that any actual or potential labor
dispute is delaying or threatens to delay the timely performance
of this contract, the Contractor shall immediately give notice,
including all relevant information, to the Contracting Officer.
52.232-17 INTEREST (JUN 1996) 32.617(a)
(a) Except as otherwise provided in this contract under
a Price Reduction for Defective Cost or Pricing Data clause or
a Cost Accounting Standards clause, all amounts that become payable
by the Contractor to the Government under this contract (net
of any applicable tax credit under the Internal Revenue Code
(26 U.S.C. 1481)) shall bear simple interest from the date due
until paid unless paid within 30 days of becoming due. The interest
rate shall be the interest rate established by the Secretary
of the Treasury as provided in Section 12 of the Contract Disputes
Act of 1978 (Public Law 95-563), which is applicable to the period
in which the amount becomes due, as provided in paragraph (b)
of this clause, and then at the rate applicable for each six-month
period as fixed by the Secretary until the amount is paid.
(b) Amounts shall be due at the earliest of the following
dates:
(1) The date fixed under this contract.
(2) The date of the first written demand for payment
consistent with this contract, including any demand resulting
from a default termination.
(3) The date the Government transmits to the Contractor
a proposed supplemental agreement to confirm completed negotiations
establishing the amount of debt.
(4) If this contract provides for revision of prices,
the date of written notice to the Contractor stating the amount
of refund payable in connection with a pricing proposal or a
negotiated pricing agreement not confirmed by contract modification.
(c) The interest charge made under this clause may be reduced
under the procedures prescribed in 32.614-2 of the Federal Acquisition
Regulation in effect on the date of this contract.
52.232-37 MULTIPLE PAYMENT ARRANGEMENTS
(MAY 1999) 32.1110(e)
This contract or agreement provides for payments to the Contractor
through several alternative methods. The applicability of specific
methods of payment and the designation of the payment office(s)
are either stated-
(a) Elsewhere in this contract or agreement; or
(b) In individual orders placed under this contract or
agreement.
552.229-71 FEDERAL EXCISE TAX-DC GOVERNMENT
(SEP 1999) 529.401-71
If the District of Columbia cites an Internal Revenue Tax Exempt
Certificate Number on orders placed under this contract, the Contractor
shall bill shipments to the District of Columbia at prices exclusive
of Federal excise tax and show the amount of such tax on the invoice.
552.232-23 ASSIGNMENT OF CLAIMS (SEP
1999) (TAILORED) 532.806
In order to prevent confusion and delay in making payment, the
Contractor shall not assign any claim(s) for amounts due or to
become due under this contract. However, the Contractor is permitted
to assign separately to a bank, trust company, or other financial
institution, including any Federal lending agency, under the provisions
of the Assignment of Claims Act, as amended, 31 U.S.C. 3727, 41
U.S.C. 15 (hereinafter referred to as "the Act"), all
amounts due or to become due under any order amounting to $1,000
or more issued by any Government agency under this contract. Any
such assignment takes effect only if and when the assignee files
written notice of the assignment together with a true copy of the
instrument of assignment with the contracting officer issuing the
order and the finance office designated in the order to make payment.
Unless otherwise stated in the order, payments to an assignee of
any amounts due or to become due under any order assigned may,
to the extent specified in the Act, be subject to reduction or
set-off.
552.232-74 INVOICE PAYMENTS (SEP 1999)
532.908(a)(1)
(a) The due date for making invoice payments by the designated
payment office is:
(1) For orders placed electronically by the General
Services Administration (GSA) Federal Supply Service (FSS), and
to be paid by GSA through electronic funds transfer (EFT), the
later of the following two events:
(i) The 10th day after the designated billing office
receives a proper invoice from the Contractor. If the designated
billing office fails to annotate the invoice with the date
of receipt at the time of receipt, the invoice payment due
date shall be the 10th day after the date of the Contractor's
invoice; provided the Contractor submitted a proper invoice
and no disagreement exists over quantity, quality, or Contractor
compliance with contract requirements.
(ii) The 10th day after Government acceptance of supplies
delivered or services performed by the Contractor.
(2) For all other orders, the later of the following
two events:
(i) The 30th day after the designated billing office
receives a proper invoice from the Contractor. If the designated
billing office fails to annotate the invoice with the date
of receipt at the time of receipt, the invoice payment due
date shall be the 30th day after the date of the Contractor's
invoice; provided the Contractor submitted a proper invoice
and no disagreement exists over quantity, quality, or Contractor
compliance with contract requirements.
i(i) The 30th day after Government acceptance of supplies
delivered or services performed by the Contractor.
(3) On a final invoice, if the payment amount is subject
to contract settlement actions, acceptance occurs on the effective
date of the contract settlement.
(b) The General Services Administration will issue payment
on the due date in (a)(1) above if the Contractor complies with
full cycle electronic commerce. Full cycle electronic commerce
includes all the following elements:
(1) The Contractor must receive and fulfill electronic
data interchange (EDI) purchase orders (transaction set 850).
(2) The Contractor must generate and submit to the Government
valid EDI invoices (transaction set 810) or submit invoices through
the GSA Finance Center Internet-based invoice process. Internet-based
invoices must be submitted using procedures provided by GSA.
(3) The Contractor's financial institution must receive
and process, on behalf of the Contractor, EFT payments through
the Automated Clearing House (ACH) system.
(4) The EDI transaction sets in (b)(1) through (b)(3)
above must adhere to implementation conventions provided by GSA.
(c) If any of the conditions in (b) above do not occur,
the 10 day payment due dates in (a)(1) become 30 day payment due
dates.
(d) Notwithstanding paragraph (g) of the clause at FAR
52.212-4, Contract Terms and Conditions--Commercial Items, if the
Contractor submits hard-copy invoices, submit only an original
invoice. No copies of the invoice are required.
(e) All other provisions of the Prompt Payment Act (31
U.S.C. 3901 et seq.) and Office of Management and Budget (OMB)
Circular A-125, Prompt Payment, apply.
I-FSS-314 FOREIGN TAXES AND DUTIES (DEC
1990)
Prices offered must be net, delivered, f.o.b. to the destinations
accepted by the Government.
(a) The offeror warrants that such prices do not include
any tax, duty, customs fees, or other foreign Governmental costs,
assessments, or similar charges from which the U.S. Government
is exempt. The offeror further warrants that any applicable taxes
duties, customs fees, other Government costs, assessments or similar
charges from which the U.S. Government is not exempt are included
in the prices quoted and that such prices are not subject to increases
for any such charges applicable at the time of acceptance of this
offer by the Government.
(b) Standard commercial export packaging, including containerization,
if necessary, packaging, preservation, marking are included in
the pricing offered and accepted by the Government.
I-FSS-249-B DEFAULT (MAY 2000) FSS A/L
FC-94-2
In addition to any other clause contained herein related to termination,
the following is applicable to orders placed under Federal Supply
Schedule contracts.
Any ordering office may, with respect to any one or more orders
placed by it under the contract, exercise the same right of termination,
acceptance of inferior articles or services, and assessment of
excess costs as might the Contracting Officer, except that when
failure to deliver articles or services is alleged by the Contractor
to be excusable, the determination of whether the failure is excusable
shall be made only by the Contracting Officer of the General Services
Administration, to whom such allegation shall be referred by the
ordering office and from whose determination appeal may be taken
as provided in the clause of this contract entitled "Disputes."
G-FSS-907 ORDER ACKNOWLEDGEMENT (APR
1984)
Contractors shall acknowledge only those orders which state "Order
Acknowledgement Required." These orders shall be acknowledged
within 10 days after receipt. Such acknowledgement shall be sent
to the activity placing the order and contain information pertinent
to the order, including the anticipated delivery date.
52.216-22 INDEFINITE QUANTITY (OCT 1995)
(VARIATION-OCT 1995) FSS A/L FC-95-6
(a) This is an indefinite-quantity contract for the supplies
or services specified, and effective for the period stated. The
quantities of supplies and services specified in the contract
are estimates only and are not purchased by this contract.
(b) Delivery or performance shall be made only as authorized
by orders issued in accordance with the Ordering clause. The Contractor
shall furnish to the Government, when and if ordered, the supplies
or services specified in the contract. The Government shall order
at least the quantity of supplies or services designated in the
contract as the "minimum."
(c) Except for any limitations on quantities in the Guaranteed
Minimum clause or Order Limitations clause, there is no limit on
the number of orders that may be issued. The Government may issue
orders requiring delivery to multiple destinations or performance
at multiple locations.
(d) --- Any order issued during the effective period of
this contract and not completed within that period shall be completed
by the Contractor within the time specified in the order. The contract
shall govern the Contractor's and Government's rights and obligations
with respect to that order to the same extent as if the order were
completed during the contract's effective period.
52.216-19 ORDER LIMITATIONS (OCT 1995)
(VARIATION I—AUG 1999) (TAILORED)FSS A/L FC 95-6
(a) Minimum order. When the Government requires supplies
or services covered by this contract in an amount less than $300,
the Government is not obligated to purchase, nor is the Contractor
obligated to furnish those supplies or services under the contract.
However, offerors may, if willing to accept smaller orders, specify
a smaller amount in their offers. If a smaller amount is offered,
it is mutually agreed that the Contractor will accept such orders
and specify the smaller minimum order limitation in the applicable
catalog/pricelist. If the offeror fails to specify a smaller
amount, the Government may place orders for a smaller amount.
Such orders shall be deemed to be accepted by the Contractor,
unless returned to the ordering office within 5 workdays after
receipt by the Contractor.
(b) Maximum order. The Contractor is not obligated to
honor any order for a combination of items in excess of:
ITEM NUMBER/SIN MAXIMUM ORDER
ALL ITEMS $1,000,000.00
(c) Notwithstanding paragraph (b) above, the Contractor
shall honor any order exceeding the maximum orders in paragraph
(b), unless that order (or orders) is returned to the ordering
office within 5 workdays after receipt, with written notice stating
the Contractor's intent not to ship the item (or items) called
for and the reasons. Upon receiving this notice, the Government
may acquire the supplies or services from another source.
(d) Notwithstanding paragraph (b) and (c) above, the Contractor
shall honor any purchase card orders exceeding the maximum orders
in paragraph (b), unless that order (or orders) is returned to
the ordering office within 24 hours after receipt, with written
notice stating the Contractor’s intent not to ship the item
(or items) called for and the reasons. Upon receiving this notice,
the Government may acquire the supplies or services from another
source.
Next